Supply and Maintenance of the JANET Core Videoconferencing Equipment

JANET(UK) has selected Direct Visual as preferred supplier.

----------------------------------------------------------------------------------------------------------------------------------------

This procurement is to appoint a single supplier to supply suitable equipment and to provide its maintenance.  The contract will form a framework agreement that JANET(UK) will use for initial purchase and a phased replacement of the existing core equipment including the gatekeeper hierarchy and networking equipment over the next few years.

The Prequalification Questionnaire (PQQ) is available electronically below as a Word file and an Adobe PDF file.

Clarifications

As matters for clarification arise they will be answered by JANET(UK) and made available on the JANET(UK) e-tendering opportunities portal. Suppliers that have registered their intent to submit a proposal will be notified each time this is updated.

Registration

Suppliers should note that before submitting a response to the PQQ they must register their intent to do this with JANET(UK).

Each potential supplier must register on the new JANET(UK) e-tendering opportunities portal at https://tenders.ja.net. Each potential supplier must register as a system user if they are a first time user of the JANET(UK) portal, which is a one-off activity. Once accepted by JANET(UK), each supplier will receive a username and password that should be used for all future accesses to the system. The only time that JANET(UK) will reject a supplier is if there is an attempt to have a duplicate registration for a supplier. Also, please note that this first time registration is not a registration for a particular contract, it is only the registration of the user on the JANET(UK) portal. When username and password are received, then a supplier must log in and then register their interest in a specific contract. It is recommended that a generic mailbox (such as sales@supplier) is set up, so that information from the system can be sent to more than one representative at the company.

The steps and timetable for this procurement are as follows:

Activity

Date

Insert Notice of procurement launch in the EU Journal

28th January 2008

Close of registration to take part in procurement process

26th February 2008

Final date for clarifications

26th February 2008

Prequalification Questionnaire returns

12:00 Noon on Tuesday 4th March 2008

Complete review of responses and shortlist suppliers to receive the Operational Requirement

28th March 2008

Final date for clarifications

Wednesday 30th April 2008

Operational Requirement returns

12:00 Noon on Wednesday 7th May 2008

Selection of preferred supplier

30th May 2008

Contract placed with the preferred supplier

20th June 2008

 Equipment installed and commissioned

29th August 2008

JANET(UK) reserves the right to vary this timetable if the need arises, within the constraints of the European Directive.